The Brihanmumbai Municipal Corporation (BMC) has proposed a new policy to make utility agencies more accountable for excavation and road repairs across mumbai. The proposed Comprehensive Trenching and Reinstatement Policy 2026 includes stricter penalties for unauthorised digging, longer defect-liability periods and mandatory digital mapping of underground utilities.

The proposal will be reviewed by the BMC Standing Committee on Thursday, October 8. The new framework will improve coordination between utility agencies and the civic body.

Under the proposed policy, the reinstatement fee for utility work on under-construction roads will be reduced from INR 6,711 per metre to INR 2,300 per metre. The BMC said the lower fee is intended to encourage agencies to coordinate their utility work with ongoing road projects. This could avoid newly constructed roads being excavated again for utility work.

The draft also proposes a penalty for unauthorised trenching. Agencies carrying out excavation without approval would face a fine equal to five times the standard reinstatement fee.

Trenching would also be restricted to designated time windows. Agencies carrying out work outside these periods would require approval from the municipal commissioner and would have to pay an additional 10% of the reinstatement fee.

Emergency repairs would be permitted through an online application and coordination with local authorities. In such cases, the assistant commissioner would have to inform the municipal commissioner about the work within 24 hours.


The proposed policy would also extend the responsibility period for utility agencies. The current three-year defect-liability period would be replaced with 10 years for cement-concrete roads and five years for non-cement-concrete roads. For trenching on concrete roads, agencies would be required to use diamond cutters. Reinstatement charges would also be calculated based on the size of the trench.

The BMC has proposed mandatory GIS-based Web Map Service mapping of underground utilities. Agencies would have to update the digital records within 30 days of completing their work. Agencies that fail to provide the required information would not be allowed to undertake further trenching until the mapping data is updated.

The draft also requires low-voltage telecom and electricity agencies to use existing utility ducts for wires up to 100 mm wherever possible. If a suitable duct is not available, the agency would have to construct one or request the Roads Department to construct it.

The civic body has proposed simplifying the road surface categories used to calculate reinstatement charges. The existing 16 categories would be reduced to two broad groups: cement-concrete and non-cement-concrete roads. A uniform access fee of INR 20 per metre, including GST, has also been proposed for all utility providers.

For horizontal directional drilling, which allows underground utilities to be installed with less disruption to the road surface, the draft proposes a security deposit of INR 15 lakh per kilometre.

Agencies carrying out routine trenching would also be required to submit a deposit equivalent to 50% of the applicable reinstatement fee, subject to the conditions specified in the proposed policy. Utility agencies will also regrade trenches themselves under civic supervision. The cost of this self-reinstatement arrangement would be 10% of the applicable reinstatement fee.