Central Railway (CR) will operate 11 days Special Traffic Block from August 4, 2026 to August 14, 2026 for balance work of construction at Lokmanya Tilak Terminus (LTT) including work related to construction of shunting neck, sick siding modification of the existing, maintenance siding yard, extension of pit lines in maintenance sidings no 6,7,8,9 and diversion of water supply line, drainage and storm water line.
Date and duration of block: From 08.00 hrs of 04.08.2026 (Tuesday) to 08.00 hrs of 14.08.2026 (Friday) – 11 days
Line Affected:
Sick collection line and Washing pit line no 6, 7 & 8
Stabling line no 5, C&W sick line no 1, 2, 3 & 4
Following Trains will be Short Terminated at Thane :
These blocks are essential for infrastructure upgradation and safety. Passengers are requested to bear with the Railways for the inconvenience caused and are requested to kindly take note of the repercussions and plan their travel accordingly.