5 Major Infrastructure Projects in Mumbai Face Delay; Escalates Cost By ₹2,676 Cr

On the other hand, civic officials stated that big projects like GMLR, DBLR, coastal roads are the first of its kind here and it takes time to complete and sometimes delays the work.

5 Major Infrastructure Projects in Mumbai Face Delay; Escalates Cost By ₹2,676 Cr
(File Image)
SHARES

According to a latest report, it has come to light that the delay in completing several bridges in Mumbai has resulted in cost escalation of these projects.

They include, Dahisar-Bhayander Link Road (DBLR), Goregaon-Mulund Link Road (GMLR), Vidyavihar rail over bridge (ROB), Vikhroli East-West Bridge and Delisle bridge.

Activists and political leaders have raised concerns about the recent increase in cost of these projects.

On the other hand, civic officials stated that big projects like GMLR, DBLR, coastal roads are the first of its kind here and it takes time to complete and sometimes delays the work.

Dahisar-Bhayander Link Road (DBLR):

A Congress leader has requested the Chief Minister Eknath Shinde and Deputy Chief Minister Devendra Fadnavis to look into the matter and stop the practice of cost escalation of DBLR. In addition to this, the construction cost issue has also been raised by activists and ex-corporator.

The ambitious DBLR project, which will ease connectivity between the island city and the western suburbs has seen a cost escalation even before its construction started.

Ravi Raja, former opposition leader of the BMC and senior Congress leader said, “The estimated cost of the project was ₹1,600 crore in 2016 and has now increased to ₹4,000 crore while the project is still under tendering stage. The civic body’s lack of planning has resulted in a waste of taxpayers’ money. Do the administrators think that they are not answerable to anyone? We have requested the chief minister to take the necessary steps to stop such malpractices in the BMC.”

GMLR project

The estimated cost of building the twin tunnels as well as renting a casting yard and the disposal of debris has raised the cost of the Goregaon Mulund Link Road (GMLR) project by ₹132 crore.

Delisle Bridge:

The Delisle bridge in Lower Parel has seen a cost escalation of ₹14 crore due to several delays in the past five years.

Vikhroli East-West Bridge:

The estimated cost of the bridge has escalated from ₹45.77 crore to ₹97.37 crore, while the new estimated completion date is June 2024.

East-West connectivity in Vikhroli has been an issue ever since the level-crossing gate was shut 10 years ago. After consistent efforts by the locals and activists, a work order was issued for the bridge in May 2018, an activist exclaimed.

Vidyavihar ROB:

The actual cost of the bridge was ₹99.98 crore, which rose to ₹108 crores after the railways made some changes to the design. The length of the bridge was also increased, which led to the cost rising to ₹178.93 crore, and the new deadline is mid-2024, civic sources informed.

The citizens have to suffer due to the incompletion of the project. There will be no delay in obtaining various permissions if the railway administration initiates a single window scheme in such a project, suggested an activist.