The Union Budget's total plan outlay (net) for FY 2022-23 for Central Railways is INR 7,251 crores which is an increase of 50 per cent as compared to 2021-22.
Here are the highlights:
New lines – Rs.1455 crore
Ahmednagar-Beed-Parli Vaijnath 250 km Rs.567 crore
Wardha-Nanded via Yevatmal Pusad 270 km Rs.820 crore
Solapur-Osmanabad via Tuljapur 84 km Rs.10 crore
Dhule-Nardana 50 km Rs.50 crore
Kalyan-Murbad via Ulhasnagar 28 km Rs.5 crore
Doubling / 3rd Line / 4th Line – Rs.3628 crore
Kalyan-Kasara 3rd line 68 km Rs.160 crore
Wardha-Nagpur 3rd line 76 km Rs.87 crore
Wardha-Balharshah 3rd line 132 km Rs.305 crore
Itarsi-Nagpur balance 280 km Rs.610 crore
Pune-Miraj-Londa doubling 467 km Rs.1567 crore
Daund-Manmad doubling 247 km Rs.500 crore
Wardha-Nagpur 4th line 79 km Rs.130 crore
Manmad-Jalgaon 3rd line 160 km Rs.205 crore
Jalgaon-Bhusaval 4th line 24 km Rs.55 crore
Traffic facilities, yard remodelling and other works –
Panvel-Kalamboli coaching terminus Phase-I stage-I Rs.20 crore
Lokmanya Tilak Terminus augmentation of coaching facilities Rs.20 crore
CSMT extension of platform 10, 11, 12, 13 for 24 coaches Rs.20 crore
Hadapsar development as satellite terminal Rs.21 crore
Ajni development as satellite terminal Rs.35 crore
Pune extension of platform for 24/26 coaches Rs.31 crore
Road safety works – ROB / RUB
Vikhroli ROB Rs.6 crore
Pulgaon ROB Rs.5.5 crore
Nagargaon ROB Rs.4.33 crore
Diva ROB Rs.4 crore
Provision of 115 escalators at platforms Rs.23.92 crore
Badnera wagon repair workshop Rs.30 crore
Ratnagiri rolling stock component factory Rs. 30 crore
Soft upgrade improvements at stations Rs.13.5 crore
FOB at stations Rs.60.67 crore
Provision of 143 lifts at stations Rs.34.18 crore
Construction of boundary wall Rs.10 crore
Metropolitan Transport Projects
Belapur-Seawood-Uran line Rs.150 crore
MUTP Phase-II Rs.185 crore
MUTP Phase III Rs.190 crore
MUTP Phase III-A Rs.200 crore
Track Renewals – Rs.1048 crore
Bridge works, Tunnel works Rs.90 crore
Signalling and Telecommunication works Rs 216 crore