Mumbai Rains: Central Railway gears up with monsoon preparations

To ensure smooth and disruption-free services during the ensuing monsoon, Central Railways has geared up with monsoon preparations.

Mumbai Rains: Central Railway gears up with monsoon preparations
SHARES

Anil Kumar Lahoti, General Manager, Central and Western Railways reviewed the monsoon preparations of Central and Western Railway. Principal Head of Departments and Divisional Railway Managers of the Mumbai division were also present. Senior Officers of Mumbai divisions gave presentations on the monsoon preparations done by the respective Railways.

Guiding the officers, Lahoti said that all monsoon related work should be completed before the target date. He also instructed the concerned officials to ensure 24x7 monitoring at all the vulnerable locations and to work in close coordination with State Government and Municipal Corporations.

To ensure smooth and disruption-free services during the ensuing monsoon, Central Railways has geared up with monsoon preparations such as removal of muck, cleaning culverts and drains, trimming trees, scanning boulders, provision of high wattage pumps at locations vulnerable to waterlogging, provisioning multi-section digital counters etc.

Central Railway’s Mumbai Division carried out monsoon precautionary measures on its suburban network as well as in ghats thoroughly. The details of measures taken for ensuring uninterrupted services are as under. 

Central Railway has identified 19 vulnerable locations for waterlogging during heavy rains and plans to provide 83 pumps at these locations. This year a total of 149 pumps will be provided, of which Railways will be providing 118 pumps and the Brihanmumbai Municipal Corporation (BMC) will be providing the balance 31 pumps.

This year the capacity of pumps and the number of pumps were increased at flood-prone locations to avoid flooding. The locations identified on the mainline are Masjid, Mazgaon yard, Byculla, Chinchpokli, Currey Road, Parel, Dadar, Matunga, Sion, Kurla, Vikhroli, Kanjurmarg, Bhandup, Mulund and on Harbour line are Sewri, Vadala, Guru Tegh Bahadur Nagar, Chunabhatti, Tilak Nagar etc.

Central Railway (CR) has de-silted and cleaned 59 Kms of drains on its suburban section and work is presently in progress on cleaning another 59 km of drains.

CR has cleaned 38 culverts in its suburban sections, and work is presently in progress on cleaning 45 more culverts.

Work of cutting and trimming trees has been undertaken at 7,893 different places and work is in progress.

CR has set a target of cleaning and removal of 1.75 lakh cubic meters on Main and Harbour lines.

334 boulder scanning and dropping work has been undertaken in the ghat section and work is in progress for another 260 nos.

Besides work of Boulder netting and tunnel portal to prevent falling of boulders have also been undertaken in the ghat sections.

Pipe pushing via micro tunnelling between Kurla and Vidyavihar stations, two pipelines with a 1.8-metre diameter of 70-metre-long have been pushed, increasing the capacity of the culvert.

Augmentation of the waterway of the existing bridge with the insertion of RCC Boxes between the Vadala and Raoli sections will increase the waterway capacity.

Similarly, the waterway is augmented at Tilak Nagar Bridge with the insertion of RCC Boxes at Tilak Nagar Station creating a 4.9-metre extra opening to increase the waterway capacity. Also, the enhancement of the bridge waterway by insertion of an RCC Box adjacent to the existing bridge between Panvel and Karjat has increased the waterway capacity and a 1.8-meter diameter pipe was pushed between Badlapur and Vangani to increase the water flow. Central Railway has replaced the steel girder with a PSB slab of the important Waldhuni Bridge.

Important works targeted for completion

•    3 locations in the Sion-Kurla area to be under observation for the effectiveness of work done this monsoon.

•    Pumping arrangements at Rahul Nagar nullah, Chunabhatti to be completed before this monsoon.

•    Bunter Bhavan nullah at LTT to be connected by removing encroachments.

•    Karve Nagar nullah improvement work to be done by MCGM and cost to be recovered from Ajmera builders.

•    Appointment of consultant for work of clearing of concrete deposited below water mains at Priyadarshini, Chunabhatti.

Important work in progress

•    Widening of nallahs at Vidyavihar, Karve Nagar, Santoshi Mata nallah.

•    Connection work of newly constructed Railway culverts to MCGM drain at Chunabhatti.

•    Installation of CCTVs at 145 vulnerable locations in the ghat section with floodlights.

Important works completed

•    Micro tunnelling at Masjid, Sandhurst Road, Hindmata-Dadar-Parel area completed.

Other important works:

•    Installation of flood gates at Masjid, Byculla, Matunga and Sion-Kurla areas.

•    MSF Jawans + RPF Staff as quick response teams.

•    A RPF Flood Rescue Team formed in collaboration with NDRF.

•    Critical FOBs identified & staff deployed for crowd control.

•    Improved communication system in Tunnel and Ghat. (leaky cable and VHF)

•    Additional static watchmen at vulnerable locations

24X7 Control Room

CR Control office, working round the clock, will keep close liaison with Meteorological Department, Disaster Management cell and staff deputed at flood-prone areas for continuous monitoring and constant updates.