Will take action against engineer for delaying repair work in civic schools: TMC Commissioner

TMC commissioner had directed to take up the repair work of the buildings and complete it as soon as possible

Will take action against engineer for delaying repair work in civic schools: TMC Commissioner
SHARES

INR 15 crores have been approved under the building repair of municipal schools so that the students studying in municipal schools should develop affection towards school and education. Thane Municipal Commissioner (TMC) Abhijit Bangar had directed to take up the repair work of the buildings and complete it as soon as possible after issuing the order for the school repair work. Accordingly, notices have been issued to the concerned executive engineers of some schools whose works are on the way to completion, schools whose works have not yet started or some schools whose works are progressing at a slow pace, and if the notice is not disclosed within the prescribed period, disciplinary action will be taken, the commissioner said.

There is constant movement of students in schools, so the repair of schools needs to be prioritised to avoid any accidents. Due to the fact that the repair work of the schools was not completed even though the task order was given in March 2023, Bangar said notices were sent to the concerned executive engineers.


Also Read: BMC Demolishes Slum In Bandra; Residents' Wait Continues For Promised Homes


A total of 34 school repair works in Thane Municipal Corporation area which require repair is INR 14,99,95,000/- and the consolidated tender was released under the year 2022-23, Commissioner Bangar mentioned. The tender covers the repair of schools in each Ward Committee area, of which only 5 schools have been 100 percent completed. The repair work of 9 schools has been completed more than 50 percent. But the repair work of 8 schools is going on slowly and the said works are very unsatisfactory. And the repair work of 12 schools has not started.

Thane School in Wagle Division No. 40 percent of 23, Kalwa division school no. 30 percent of schools 129, 69, 70, 115, 29, Majiwada Manpada School no. 53, 54 and 25 percent of schools 46 in Lokmanya Savarkar Nagar division, Vartak Nagar division school no. 65 and Mumbra Division School No. 75, 20 percent of 118 has been completed.


Schools not yet operational

Kalwa Division School No. 4,6,72,68, Majiwada Manpada Division School No. 59,52,128, Mumbra Division School No. 78,123,113,77,124,116, Diva Division school No. 85,90,91 while school No.16 in Naupada Division has not yet started the work of these schools. A notice has been issued to the Executive Engineers entrusted with the work of these schools and a written explanation has been sought regarding the incomplete works. It has also been mentioned in the notice that if the disclosure is not submitted within the prescribed period, disciplinary action will be taken against the concerned.