35th phase in the Metro-3 underground project completed

The tunnelling was completed by Krishna-1, a TBM manufactured by Herrenknecht Company which incorporated the Earth Pressure Balance (EPB) technology. This phase of work was started on July 7, 2020

35th phase in the Metro-3 underground project completed
SHARES

The 35th phase in the underground work of Metro-3 was recently completed by the officials. As per the plan, this 1.12 km stretches from Siddhivinayak to Dadar, and the reports for the finished work were released on December 16, 2020. With this phase of the underground project, a total of 10.96 km of the Package 4 was completed on Wednesday. 

It is said that a total of three Tunnel Boring Machines (TBM) were being used for this phase.

Officials also state that the underground work has been completed 100 per cent in four out of the seven packages on the proposed Metro 3 project. The underground work in Package 4 was a big challenge as all the development works in this package were closer to road transports and religious places.

The tunnelling was completed by Krishna-1, a TBM manufactured by Herrenknecht Company which incorporated the Earth Pressure Balance (EPB) technology. This phase of work was started on  July 7, 2020, and the downline work has been completed using 805 rings. 

With this, 42 per cent of Dadar Metro Station work was completed, stated SK Gupta, Project Director of Mumbai Metro Rail Corporation (MMRC).

The proposed plan for this package of the Mumbai Metro project includes Dadar, Siddhivinayak, Shitladevi stations. Till date, a total of eight underground phases have been completed here.