Mumbai Local News: Newly-launched 6th Line Between Khar-Goregaon To Improve Punctuality

This project will enhance the line capacity of Mumbai suburban section and will help to ease the congestion, improve punctuality and help to add more train services.

Mumbai Local News: Newly-launched 6th Line Between Khar-Goregaon To Improve Punctuality
SHARES

Western Railway successfully completed the infrastructural work and made a trial run of 6th line o­n the 8.8 km stretch between Khar RoadGoregaon o­n November 5, 2023. A day later, November 6, it commenced the operations and achieved Speed Trial of 112 kmph over this section.

The work which commenced o­n October 7, 2023, consisted of Pre-Traffic Work Order of 30 nights and Traffic Works Order (TWO) of 29 nights including Non-Interlocking work (NI) of 10 nights at 6 stations has been completed and all the train services have been fully restored from November 6, 2023.

In an official statement released, Sumit Thakur, Chief Public Relations Officer of Western Railway, said that the entire work involved laying of 12 Turnouts and three Trap point o­n the existing 5th line and both the Fast lines. It also involved laying of 8 Turnouts o­n the new 6th Line and dismantling of existing nine Turnouts & three Trap points from the existing lines. An independent connectivity to both 5th and 6th lines have been provided to Bandra Terminus Yard after slewing of 700m existing track and dismantling of five points including a diamond crossing. Heavy machineries such as T-28, UNIMAT, Duomatic, UTV, Hydraulic Cranes, JCBs etc. were deployed to carry out the work smoothly and efficiently.

Thakur further informed that the work involved land acquisition of Private land as well as Government Land (BMC). Further, 27 new FOBs have been constructed in lieu of existing FOBs which were infringing the alignment. Also, existing railway structures which were obstructing were dismantled and new structures were constructed in lieu of them. This involved construction of new Railway Quarters of 192 flats, six new Electronic Interlocking (EI) buildings, two new Traction Sub Station (TSS) buildings, three Booking Offices etc. Around 607 Project Affected People (PAPs) were rehabilitated and provided with alternate allotments. Also, almost 1000 trees have been relocated & transplanted.

Thakur informed that this project will enhance the line capacity of Mumbai suburban section and will help to ease the congestion, improve punctuality and help to add more train services.